Building Permits
Finland
Duration
8 – 16 weeks
Paperwork Mountain
Drawings Required
75%
Permit Headache
Tips
- There is a one-month appeal period after granting of a permit where third party objections can be raised.
DID YOU KNOW?
- Environmental Impact Statements can be granted in parallel with the Building Permit.
- Piling and foundations may be permitted prior to the full permit being granted.
- Final inspections must be carried out by the authorities and self-certifying by professionals is not permissible.
Any questions? Don’t hesitate to contact us.
The previous info is intended as broad guidance – every site varies. Contact Tony for tailored permitting advice relating to Finland.
-